In their capacity as chairmen of the committees for Energy and Oversight respectively, Waxman and Stupak delivered a letter to the BP CEO, prior to his testimony, in which he is asked to prepare himself to address the allegations that BP
*Went against the advice of its own plan review regarding the well's design and chose a riskier, cheaper and quicker casing option
*Used only 6 centralisers to make sure the casing ran down the centre of the well bore, rather than the 21 recommended by sub-contractor Halliburton
*Rejected warnings by its own plan review (and Halliburton) in preparations for a cementing job
*Decided to forego a recommended safety step in the circulation of drilling mud, and
*Did not deploy a "lockdown sleeve" that would have prevented the seal from being blown out from below.
In his subsequent testimony, Hayward arguably failed to address these allegations adequately.